Data centre construction cost increases of up to 8% across region year-over-year but development shows no sign of pausing

Amy Kathleen Kelly • 06/11/2023
  • Average construction cost increase of 4.9% across Asia Pacific key markets

  • Mature markets dominate data centre land, construction cost indexes

  • Data centre development activity across the region remains “significantly elevated”

Japan has been named the most expensive market for data centre construction while Singapore has topped the rankings for the most expensive land costs in Asia Pacific, according to a new report.

Mature markets dominated the top five positions for both the Regional Construction Cost Index and the Regional Land Cost Index included in Cushman & Wakefield’s inaugural Data Centre Construction Cost Guide.

Report author and Head of Asia Pacific Data Centre Construction, Project Development Services, James B. Normandale said:

“The market is facing some of the highest development rates in data centre market history. This is the result of persistent – although improved – supply chain disruption and construction market inflation, as well as higher capital lending rates across most markets within Asia Pacific. Despite the increased costs, development activity across the region remains significantly elevated as the sector continues to grow in response to secular trends, industry incentives, regulatory relaxation, and interest from investors who see opportunity in the disparity between future population needs and existing IT capacity.”

Figure-1-Regional-Construction-Cost-Index
Based on a medium specification, 10-50MW data centre build (refer p19 of report).

Demand and domestic pressures influence land cost

Singapore’s limited land supply and government restrictions on data centre development saw the city-state top South Korea, Hong Kong China, Japan and mainland China for the most expensive market for land cost. The Regional Land Cost Index was calculated based on suburban industrial land (medium range) rather than central business district (high range) or industrial outskirts (low range) and based on the average cost of key cities within a market. Among a comparison of cities (see Figure 3), Singapore recorded the top price of USD11,573 per square metre (sqm), above Seoul (USD10,525) and Busan (USD8,865).

Figure-2-Regional-Land-Cost-Index
Based on suburban industrial land and averaged across key cities within a market (refer p15 of report).

Development costs elevated overall

The average construction cost increase on 2022 was 4.9% across Asia Pacific. Singapore recorded the greatest increase (8%), while Australian and New Zealand recorded the smallest increase (3.5%).

Figure-3-Land-Cost-by-City-v2
Based on suburban industrial land (medium range) where available (refer p15).

Key Trends Impacting the Data Centre Sector

  • Power, Location & Management
    The rise of AI and ML, while still in its infancy, is expected to drive substantial changes within the data centre sector. These technologies are increasing power consumption, rack loading requirements, and overall site capacity. Unlike traditional data centres, AI data centres for remote learning can be built between 450km and 1,000km from established data centre locations using existing low-latency infrastructure. While this may help to relieve pressure on land and power in densely populated areas, it could create labour and supply chain challenges.
  • Environmental, Social & Governance (ESG)
    There is a growing emphasis on holistic performance measurement within the sector, encompassing financial performance, ethical conduct, societal contributions, and environmental responsibility. Data centre operators are experimenting with sustainable power and zero-carbon electricity options, resulting in operational improvements and cost savings. The adoption of AI-driven software for data centre operations has started to demonstrate improvements in Power Usage Effectiveness (PUE) ratios.
  • Strategic Sourcing & Supply Chain
    Though improved, supply chain disruption driven by geopolitical uncertainty and economic unpredictability continues to impact costs. This trend is expected to persist into 2024 and has prompted the sector to adopt more conservative approaches to material and resource planning, such as multi-vendor supplier strategies.

“The data centre sector in Asia Pacific is in a dynamic phase as it undergoes further growth and innovation. The colocation market size was reported to be USD25.5 billion in 2022 and it is expected to reach USD51.8 billion by 2028 – a Compound Annual Growth Rate of 12.5%. Hyperscale cloud revenue is expected to grow at 19% CAGR through now and 2028. Investors who stay abreast of developments in the AI and ML space will be well-placed to capitalize on these growth opportunities,” said Mr. Normandale.

About the Asia Pacific Data Centre Construction Cost Guide 2023

The guide tracks 37 key data centre locations across Asia Pacific with a comprehensive breakdown of costs covering land acquisition, advanced land clearance and demolition works, base build and fit-out construction costs. It offers a comprehensive analysis of the Asia Pacific data centre landscape, including key trends that are shaping the region's data centre sector. This is the first year that Cushman & Wakefield has published its data centre development cost data. Read the Asia Pacific Data Centre Construction Cost Guide here.

Recent Press Releases

APAC DC H2 2025
press release_thumbnail_DC_Andrew Green.jpg
Asia Pacific Data Centre Leadership Strengthened Amid Rapid Market Growth

Asia Pacific’s data centre market is projected to triple in size over the next five years. To capture this growth, Cushman & Wakefield has strengthened its Data Centre leadership team across the region, led by Andrew Green, Head of Data Centre Group, Asia Pacific.

Chek Yee Foo • 29/01/2026

GWS - Charli Chan - Image Tile.jpg
Meet Charli Chan, Market Leader in Greater China Cross-border Investments

Since joining Cushman & Wakefield in 2014, Charli Chan has set the industry benchmarks for facilitating complex, high-value real estate transactions between the Chinese mainland and Hong Kong.

Charli Chan • 27/01/2026

Suntec City Photo 1.jpg
High Floor Strata Units at Suntec City with Panoramic Views For Sale

Cushman & Wakefield (S) Pte Ltd (“C&W”), the exclusive marketing agent, is pleased to announce the launch of an opportunity for investors to acquire prime strata office units located on prestigious high floors of Suntec Tower, one of Singapore’s most iconic integrated developments.

Shaun Poh • 22/09/2025

Set-up office example in Tokyo
Asia Pacific’s Office Market Enters a New Era of Strategic Maturity

Asia Pacific’s office market is entering a new era of strategic maturity, driven by a decade of rapid expansion and growing demand for future-ready, innovation-driven workspaces.

Amy Kathleen Kelly • 19/09/2025

C&W Services - Champion of Good thumbnail.png
C&W Services Singapore Honoured as Champion of Good by NVPC

C&W Services Singapore is proud to be recognised as a Champion of Good, the highest accolade under the National Volunteer & Philanthropy Centre’s (NVPC) Company of Good Recognition System.

Jacyn Kang • 11/08/2025

Malaysia_CrdImge.jpg
Malaysia the fastest growing data centre market in Asia Pacific

Cushman & Wakefield, a global real estate services company, has released its Asia Pacific Data Centre H1 2024 Update.

Amy Kathleen Kelly • 18/09/2024

Data-Center-Singapore.jpg
Singapore ranks 6th in Established Markets for Data Centers

Singapore continues to be a leading data center hub for its regional and global connectivity, despite the high property and construction costs when compared to neighbouring South-East Asian markets and other primary markets in Asia Pacific. 

Nandhini Rad • 06/06/2024

With your permission we and our partners would like to use cookies in order to access and record information and process personal data, such as unique identifiers and standard information sent by a device to ensure our website performs as expected, to develop and improve our products, and for advertising and insight purposes.

Alternatively click on More Options and select your preferences before providing or refusing consent. Some processing of your personal data may not require your consent, but you have a right to object to such processing.

You can change your preferences at any time by returning to this site or clicking on Privacy & Cookies.
MORE OPTIONS
AGREE AND CLOSE
These cookies ensure that our website performs as expected,for example website traffic load is balanced across our servers to prevent our website from crashing during particularly high usage.
These cookies allow our website to remember choices you make (such as your user name, language or the region you are in) and provide enhanced features. These cookies do not gather any information about you that could be used for advertising or remember where you have been on the internet.
These cookies allow us to work with our marketing partners to understand which ads or links you have clicked on before arriving on our website or to help us make our advertising more relevant to you.
Agree All
Reject All
SAVE SETTINGS